Paid detour from Krasnodar on M4 “Don” will open on June 10
- May 10, 2023
- 0
The head of Avtodor, Vyacheslav Petushenko, spoke about the deadlines for completing the next section of the M4 Don highway. The statement was made during the report of
The head of Avtodor, Vyacheslav Petushenko, spoke about the deadlines for completing the next section of the M4 Don highway. The statement was made during the report of
— We have two bottlenecks: bypassing Aksai and bypassing the DZOK (“Far Western Bypass of Krasnodar”). This is 86.7 km of new roads, which we will deliver one and a half years earlier. The plan is to open up the route on 10 June, so that we can expand the bottlenecks. We know that the M4 highway is the most popular nowadays,” Petushenko said during a meeting with the Prime Minister of the Russian Federation.
Recall that at the end of January 2023, by order of the government until June 30, 2122, a paid mode of travel was introduced along the Far Western Bypass of Krasnodar section of the M4 Don highway. As a free alternative, two routes are offered to drivers.
The first includes the Krasnodar-Yeisk highway, Krasnodar itself, the A-289 highway and the A-290 highway. The length of this route is 58 km. The second runs along the M4 Don highway, then through the city of Krasnodar, and then also along the A−289 and A−290 highways. The length of this variant of the bypass of the new payment site is 64 km.
— We have two bottlenecks: bypassing Aksai and bypassing the DZOK (“Far Western Bypass of Krasnodar”). This is 86.7 km of new roads, which we will deliver one and a half years earlier. The plan is to open up the route on 10 June, so that we can expand the bottlenecks. We know that the M4 highway is the most popular nowadays,” Petushenko said during a meeting with the Prime Minister of the Russian Federation.
Recall that at the end of January 2023, by order of the government until June 30, 2122, a paid mode of travel was introduced along the Far Western Bypass of Krasnodar section of the M4 Don highway. As a free alternative, two routes are offered to drivers.
The first includes the Krasnodar-Yeisk highway, Krasnodar itself, the A-289 highway and the A-290 highway. The length of this route is 58 km. The second runs along the M4 Don highway, then through the city of Krasnodar, and then also along the A−289 and A−290 highways. The length of this variant of the bypass of the new payment site is 64 km.
Source: Avto Vzglyad