NASA has so far designed and developed for the lunar mission Artemis I. the strongest known as rocket Space Launch System (SLS) rocket after three attempts to complete the critical tank test, Search announced that he had decided to give The space agency plans to move the large SLS rocket from the launch pad at the Kennedy Space Center to the vehicle assembly building in the coming days.
The rocket has undergone many countdowns since April 1, but failed all tests that took place. This means subsidence for NASA on the Moon mission and many projects whose future depends on this rocket. So, what kind of path is NASA planning to take at this point? Let’s take a look at the agency’s plans together.
Work on the rocket is expected to take most of May.

Any attempt at refueling was hampered by one or more technical problems with the rocket, the mobile launch tower, or the ground systems that supplied the propellant and gas; In the latest test, conducted on Thursday, April 14, 49% of the liquid oxygen fuel tank in the core stage and 5 percent of the liquid hydrogen tank was loaded. successfully had led.
NASA had hoped to complete this practice test to troubleshoot the complex launch system so that the countdown would run smoothly when the rocket actually launched later this year; but the bill at home doesn’t seem to fit the bill.
In a statement on the matter, NASA expects its contractors and agency to spend the coming weeks in the wake of the SLS rocket tank tests. To solve problems It registers what you are going to use it for.
On the other hand, the agency’s statement contained no information about the effects of this move back on the program. not given†It looks like it will take about a week to prepare and return the SLS rocket to the Vehicle Assembly Building, and work on the rocket at this location is likely to be at least most of May is expected to be covered.
So which path can NASA expect to take?

After the completion of this phase, NASA will face some difficult decisions. Accordingly, the space agency could attempt to roll the rocket and mobile launch tower a second time onto the ramp and complete the rehearsal test.
Then, following normal procedure, NASA must return the rocket to the assembly building to activate the “flight safety system” before rolling onto the launch pad for the third time to take off. One such scenario would be that the SLS rocket could be launched. earliest date is August means it will.
Another option NASA could pursue is to launch the project, test it and, if successful, launch the rocket within a few days. An example of such a scenario is NASA’s SLS rocket.me june or july means it can be launched in months; but this risky due to flight safety system will be.

Artemis Launch Director, Charlie Blackwell-Thompson, made a statement on the subject after the flight safety system was installed. 20 days It means there is a timeline. Once the system is up and running, it will take up to a week for final preparations to be made and rolled out in the Vehicle Assembly Building.
This is left only for tank testing, product recycling, and one or two launch attempts until the end of the 20-day period. a week indicates residence. In other words, this means that the test and the launch attempt must run flawlessly. Of course, in this case, Florida weather conditions must be appropriate for the situation.
Finally, NASA engineers noted that, such as wear and tear on the rocket, external exposure of the side-mounted boosters, and a seemingly large number of hardware-related issues. some other factors must also be assessed.
Still, NASA believes the SLS rocket will get through this difficult process. secure looks like. “I have no doubt that we will complete this testing process and that the data will take us to the next step” Known as Blackwell-Thompson, “We’re going to take the right steps and launch this vehicle. I’m not exactly sure what that date is, but I have in mind that we will complete the test and be ready to take off to fly. doubtless no.” he adds.