Of course, it will take longer to repair the road with the strengthening of the base. With a lane width of 7 meters, road workers manage to walk about 800 meters per shift on a recycler. The repair of a stretch of 10 kilometers takes an average of one week. And the cost of work is rising by about 40%, experts say. However, this is compensated by the strength of the roadway.
Why is this technology used? Cold regeneration actually replaces the overhaul, where the worn top layers of the pavement are dismantled and new ones are applied. And as part of the repair, we get the same quality as with a major overhaul. And, of course, the cost of the work is lower, and the deadlines for its implementation are lower,” explains Denis Zamaraev, deputy director of the Department of Road Facilities of the Yaroslavl Region.
Let’s summarize. In the Yaroslavl region, cold recycling has proven to be good. This means that there is hope that in other parts of the road, during the reconstruction of which this method will be used, they will significantly improve in quality. True, only if the repairmen strictly follow the technology and approach the work as responsibly as possible. And, of course, if bureaucratic greed does not intervene in the process …